Sector: Petrochemicals
Assiut Hydrocracking Complex
E&I cable glanding and termination works for the hydrocracking complex.
- Client
- ANOPC
- Main contractor
- T.EN Technip Energies / Petrojet
- Location
- Assiut, Egypt
- Year
- 2023
Project overview
Electrical and instrumentation cable glanding and termination for the Assiut Hydrocracking Complex, from December 2023 to January 2026. The client was ANOPC, with T.EN Technip Energies as main contractor and Petrojet as contractor.
The work involved preparing and connecting cable ends to devices, connectors and other cables to create safe, continuous paths for power and signals, while protecting each connection from environmental damage.
Project gallery
9 photos
Get In Touch
From site mobilisation to final commissioning — let's talk.
Saudi Arabia — Yanbu: Building 3081, Al Rayyan Dist., Yanbu 46413, KSA